Current MEP works are 46% complete; mechanical and electrical rough-ins progressing on Floors 1–6, plumbing risers 90% complete to rooftop, and HVAC ductwork on Levels 2–4 behind schedule by 5 days due to material delay.
| Location | Activity Description | Unit | Planned Qty | Completed Qty | % Complete | Remarks | | :--- | :--- | :--- | :--- | :--- | :--- | :--- | | Level 3 Restrooms | Soil Stack Installation | No. | 8 | 8 | 100% | Pressure test passed | | Level 4 | Rain Water Pipe (RWP) | LM | 120 | 95 | 79% | On track | | Roof | Condensate drain piping | LM | 200 | 140 | 70% | Waiting for HVAC tray alignment | | BOH | Water Heater connection | Set | 2 | 0 | 0% | Starts Oct 25 |
Before we dive into the sample, let’s review the 8 critical sections every MEP report must contain:
To make this report helpful for your specific project, ensure you follow these tips: